On August 20th, The Emirates Nuclear Energy Corporation (ENEC) announced that it has safely and successfully energized Unit 3’s main power transformer and gas insulated bus. The agency said that the unit’s auxiliary power transformers and excitation transformer were energized in normal operating configuration.
The construction of the UAE’s Barakah nuclear power plant is moving ahead with Unit 1 complete, Unit 2 stands at 95%, Unit 3 at 91%, and Unit 4 at 82%.